25 May rk singh: Government crackdown soon on developers of delayed power projects: R K Singh
Singh said that all these projects (power projects) are won under the bidding process and if they miss the SCOD (scheduled commercial date of operation or deadline to complete the project), then the developer will be banned from participating in project bidding for one year.
On the second such incident, the developer will be banned for five years, Singh said, adding that he is going to put this (rule) in (policy).
Power project developers are waiting for demand to grow but this will not happen, he said.
Singh also said that until battery energy storage becomes viable, India would have to add thermal power capacity to meet the demand.
At present the battery storage is Rs 10 per unit and energy rate is Rs 2.30, he explained. He also said that he is pushing the case for another production-linked incentive scheme for grid-scale battery energy storage.